Jumaat, 21 Oktober 2011
lampu kereta pudar dan tak cerah... (only lampu plastik) or Plastic headlamp
Ini masalah universal. Tapi semalam (21 Oct 2011) saya sudah berjaya mengembalikan kilauan lampu hadapan kereta Honda Odessey seperti asal dengan cara DIY. Sungguh puas hati, lampu kembali seperti showroom dengan cost yang minimum.
Rabu, 23 Februari 2011
PLAZA RAKYAT
Apa masalah di sebalik projek ini?
The construction site of Plaza Rakyat (pictured in February 2007) has seen little activity since the project was stalled in 1997.
General information
Scope: To built 79 story building for office, residential and leisure with 157 rooms of budget hotel and 1,600 parking lots.
Time: 1996 until now (On hold and possibly canceled)
Cost: RM419.999 juta up to 1.4 billion.
Quality: Construction as a skyscraper with postmodern design
Project Manager:
Project Owner: Government of Malaysia
Stakeholder:
a. Federal Territories Minister
b. Project developer
c. Project Manager
d. Economic Planning Unit (EPU)
e. DBKL
f. Customers
Constrain: The government has decided to terminate the deal with the current developer of Plaza Rakyat following failed negotiations and an overshot deadline to revive the project.
Contractor: Main Con: Plaza Rakyat Sdn Bhd
a. PJ Indah Sdn. Bhd. (PJI) mula 22 Dec 2003 -16 Feb 2005
b. Global Upline Sdn. Bhd – until December 2009
c. New tender will be made.
Delay Factor:
a. World economic crisis 1999.
b. Contractors don’t get enough funds to run the project.
c. Crisis between the owner and the contractors.
d. Delayed court cases.
Rabu, 19 Januari 2011
Langgan:
Catatan (Atom)