Apa masalah di sebalik projek ini?
The construction site of Plaza Rakyat (pictured in February 2007) has seen little activity since the project was stalled in 1997.
General information
Scope: To built 79 story building for office, residential and leisure with 157 rooms of budget hotel and 1,600 parking lots.
Time: 1996 until now (On hold and possibly canceled)
Cost: RM419.999 juta up to 1.4 billion.
Quality: Construction as a skyscraper with postmodern design
Project Manager:
Project Owner: Government of Malaysia
Stakeholder:
a. Federal Territories Minister
b. Project developer
c. Project Manager
d. Economic Planning Unit (EPU)
e. DBKL
f. Customers
Constrain: The government has decided to terminate the deal with the current developer of Plaza Rakyat following failed negotiations and an overshot deadline to revive the project.
Contractor: Main Con: Plaza Rakyat Sdn Bhd
a. PJ Indah Sdn. Bhd. (PJI) mula 22 Dec 2003 -16 Feb 2005
b. Global Upline Sdn. Bhd – until December 2009
c. New tender will be made.
Delay Factor:
a. World economic crisis 1999.
b. Contractors don’t get enough funds to run the project.
c. Crisis between the owner and the contractors.
d. Delayed court cases.